Submission Number: 27197
Submission ID: 110866
Submission UUID: 37f1878c-9cb4-42bc-ab98-45c1be5544dc

Created: Wed, 10/02/2024 - 14:23
Completed: Wed, 10/02/2024 - 14:23
Changed: Thu, 10/03/2024 - 19:02

Remote IP address: (unknown)
Submitted by: dalia.jorge
Language: English

Is draft: No

Locked: Yes
Transportation Department
ICF Incorporated, LLC
226142
Minnesota Carbon Reduction Strategy
1052623
We needed to develop a required document for FHWA, the Carbon Reduction Strategy by Nov 2023. There was a 8-month
window of time when the contract was executed to complete this. Too much work was needed to be done to be completed by staff and the expertise to complete the work was necessary to go outside MnDOT. Additionally, ICF developed a toolkit to help us solicit for FHWA Carbon Reduction Program (CRP) funds. This included the development of a Carbon Emissions Tool (CET) that is used to determine the cost-effectiveness of carbon reduction from a project, ensuring we are being efficient and effective with our CRP funds. ICF exceeded our expectations with this work and we are now considered leaders in the nation on carbon reduction strategies, tools and the program.
Project Duration
Thu, 03/16/2023 - 00:00
Thu, 02/29/2024 - 00:00
Sun, 06/30/2024 - 00:00
Yes
{Empty}
Contract Amounts
$499977.48
{Empty}
$499977.48
Yes
STATE AND FEDERAL FUNDS
No
{Empty}
Pierce,Anna Marie
Anna.M.Pierce@state.mn.us
Very timely
Great quality work
Came in under budget and was able to amend additional tasks into the contract to meet the entire budget available
GOOD
Yes
{Empty}
5 - very satisfied