Transportation Department
Alliant Engineering, Incorporated
165005
Signal Timing Optimization for TPI
1033431
Contract was for signal timing optimization on select routes during the Twin Ports Interchange construction.
Project Duration
Thu, 08/22/2019 - 00:00
Mon, 05/31/2021 - 00:00
Sat, 08/31/2024 - 00:00
Yes
{Empty}
Contract Amounts
$239635.22
{Empty}
$239635.22
Yes
state funds and bond funds
No
{Empty}
Cooper,Erik
Erik.Cooper@state.mn.us
Contractor completed the work in a timely manor and efficiently.
Contractor provided high quality work to meet the needs of the project.
Contractors cost was fair and work came in below original budget
good
Yes
{Empty}
5 - very satisfied