Administration Dept
Preferred Electric
239313
14th Street EV Chargers
02CP0135
Install EV Chargers in 14th Street Ramp
Project Duration
Fri, 12/01/2023 - 00:00
Sat, 03/30/2024 - 00:00
Fri, 09/20/2024 - 00:00
Yes
{Empty}
Contract Amounts
$185000
$15154
$200154.63
Yes
Agency
No
{Empty}
Cindy Dillahunty
cindy.dillahunty@state.mn.us
Very punctual. Contract extension was due to additional scope and timing of Xcel setting of their transformer.
Very satisfactory.
Reasonable.
Tony Collova is a good project manager, knowledgeable in his field and conscientious of facilities' needs.
Yes
None.
5 - very satisfied