Administration Dept
Klein McCarthy
248926
Study Living Unit AC
78VA0008
To review the Stillwater and St. Cloud Correctional Facilities for options/cost for short term upgrades and long term upgrades to the facilities vs replacement. Historical consideration was necessary as both properties are on the Historic Registry.
Project Duration
Thu, 05/23/2024 - 00:00
Fri, 01/31/2025 - 00:00
Thu, 01/30/2025 - 00:00
Yes
{Empty}
Contract Amounts
$244800
$0
$244800
Yes
Agency
No
{Empty}
Cindy Dillahunty
cindy.dillahunty@state.mn.us
Architect managed the schedule well and worked steadily to accomplish this goal.
DOC was involved in the decisions and layouts presented in the final report and are satisfied with the results.
Cost was comparable to others.
The DOC had no complaints on the vendor's performance during the course of the project.
Yes
None
5 - very satisfied