Commerce Dept
Barr Engineering
238944
Northland EIS
{Empty}
Environmental technical services to support preparation of environmental impact statements for a proposed energy project
Project Duration
Mon, 11/13/2023 - 00:00
Sun, 09/15/2024 - 00:00
Sat, 03/15/2025 - 00:00
Yes
{Empty}
Contract Amounts
$276890
$112000
$388890
Yes
State utility
No
{Empty}
James Sullivan
jim.sullivan@state.mn.us
Barr provided a timeline of milestones and tasks. They communicated frequently with us to make sure we knew task and project status, as well as any information bottlenecks. This approach was very successful.
Barr has a depth of knowledge and skill that showed throughout our engagement and in their work products. In particular, their analytical capacity, as well as GIS capability, were frequently called upon with short notice to complete new and emerging tasks. The level of expertise and quality of work was very high.
Given the level of effort, the number of staff, and project duration, the contractor cost was reasonable for the intended effort.
Overall, Barr provided excellent professional service with high quality results.
Yes
Nothing to report. Very positive experience.
5 - very satisfied