Transportation Department
LHB, Inc
157224
Final Design - Bridge 69903, Twin Ports Interchange
1032849
Consultant contractor was needed in order to meet project timelines.
Project Duration
Mon, 05/06/2019 - 00:00
Thu, 02/29/2024 - 00:00
Tue, 12/31/2024 - 00:00
Yes
{Empty}
Contract Amounts
$498467.74
{Empty}
$498467.74
Yes
state funds - bond funds
No
{Empty}
Stenberg,Paul Michael
Paul.Stenberg@state.mn.us
Contractor met project timelines for submittals
Contractor met expectations for a quality final plan.
Contractor was within budget.
good
Yes
{Empty}
4 - satisfied