Transportation Department
Bolton & Menk, Inc.
245379
Eagle Lake Corridor Study
1056047
The purpose of this contract was to augment an MPO-led corridor study to create a logical corridor segment, incorporating
additional intersections and a trunk highway intersection with a high crash rate, extending beyond the MPO boundary (they
cannot fund anything outside of their planning boundary)
Project Duration
Wed, 03/20/2024 - 00:00
Thu, 01/15/2026 - 00:00
Sun, 05/11/2025 - 00:00
Yes
{Empty}
Contract Amounts
$50058.65
{Empty}
$50058.65
Yes
state funds
No
{Empty}
Parker,Samuel Keyron
Samuel.Parker@state.mn.us
The contractor held to their proposed schedule throughout the process
Understandable and provided the appropriate depth to justify decision-making.
The cost was in line with the expectations for this segment.
good
Yes
{Empty}
5 - very satisfied