Pollution Control Agency
Braun Intertec
238155
Pine St. Dump Groundwater Investigation
191968/PRO20230002
This work order is a for a groundwater investigation to delineate the extent and magnitude of PFAS impacts in the vicinity of the former Pine St Dump site in Hastings, Dakota County.
Project Duration
Thu, 10/19/2023 - 00:00
Sun, 06/30/2024 - 00:00
Sun, 06/30/2024 - 00:00
Yes
{Empty}
Contract Amounts
$66918.15
$7491.89
$74410.04
Yes
State
No
{Empty}
Yodit Sheido
yodit.sheido@state.mn.us
Very satisfied
Very satisfied
Very satisfied
Very satisfied. The contractor, Braun Intertec continued the environmental investigation that was started during the previous fiscal year. The contractor was able to quickly familiarize themselves with new approaches and techniques for PFAS investigations. Moreover, the provided the project team with timely updates on the status of site activities.
Yes
{Empty}
5 - very satisfied