Submission Number: 28693
Submission ID: 131021
Submission UUID: 6a7f6164-e4a3-4a5c-bbef-dd4abbb80644

Created: Thu, 08/07/2025 - 15:14
Completed: Thu, 08/07/2025 - 15:14
Changed: Mon, 08/11/2025 - 14:46

Remote IP address: (unknown)
Submitted by: vicki.allen
Language: English

Is draft: No

Locked: Yes
Pollution Control Agency
WSP USA Environment & Infrastructure Inc.
262869
SW8 FY25 GW Delineation WSP
AI 2279 / PRO20240004
Contractor will complete groundwater investigation activities at Johnson Brothers Landfill SW-8. This includes vertical aquifer profiling and groundwater sampling at up to 9 locations on-site, the collection of groundwater samples from up to 23 monitoring wells, and installation and operation of transducers in up to 13 monitoring wells for up to 6 months. Drilling will be done by a state drilling contractor. After completion of the sample collection, contractor will deliver water samples to MDH lab for analysis. Contractor will update all site models and 3-D visualizations. The contractor will complete access coordination as well as coordinate and oversee IDW disposal as done by a state contract waste disposer. Contractor will oversee bidding and subcontractor procurement. Contractor will follow the state purchasing manual and all guidelines. Cost of MDH analysis is not covered by this work order as the MPCA will contract directly to MDH.
Project Duration
Thu, 10/16/2025 - 00:00
Mon, 06/30/2025 - 00:00
Mon, 06/30/2025 - 00:00
Yes
{Empty}
Contract Amounts
$480476.71
$40302.57
$520779.28
Yes
state
No
{Empty}
Daniel Hegrenes
daniel.hegrenes@state.mn.us
satisfied
satisfied
satisfied
satisfied
Yes
{Empty}
5 - very satisfied