Natural Resources Dept
TKDA
B46173
Willard Munger State Trail Bridge Rehabilitations
4LEGOC20
Design, contract administration, and construction observation of two bridge rehabilitation projects.

It was necessary as the DNR did not have enough staff to do this work.
Project Duration
Fri, 07/23/2010 - 00:00
Mon, 07/23/2012 - 00:00
Tue, 11/08/2011 - 00:00
Yes
{Empty}
Contract Amounts
$68900
$9800
$78700
Yes
Legacy
No
{Empty}
Paul Ouren
paul.ouren@state.mn.us
Overall good. Milestones were all met until the the State shutdown that accured in July. That delayed finishing the punchlist items, and the final documentation of the project.
Good. There were some details that were missed in the design that needed to be added into the contract during the construction phase.
Good. The final invoice amount is $72,186.66. This is $6,513.34 below the allowable contract amount of $78,700.00.
Good.
Yes
None.
4 - satisfied