VETERANS HOME BOARD
Lindell Engineering Inc.
444657
Design for Replacing B-6 HVAC Insulation
75074MPP
Design for, and bid replacement of, damaged roof top thermal pipe insulation
Project Duration
Sun, 04/17/2011 - 00:00
Tue, 12/06/2011 - 00:00
Tue, 12/06/2011 - 00:00
Yes
{Empty}
Contract Amounts
$14000.00
$-2000.00
$12000.00
Yes
Asset Preservation FY10
Yes
Within guidelines, cost savings by engineer being familiar through other current work on campus, also made them a new vendor so they wouldn't be under another consultant's mark-up.
Glen Heino
glen.heino@state.mn.us
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Excellent – The Consultant performed in a better than average manner that demonstrating a good understanding of the owner’s requirements and contract requirements. The consultant’s overall performance outweighs any negative performance. The Consultant contributed a great deal to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Yes
{Empty}
4 - satisfied