Submission Number: 12894
Submission ID: 63358
Submission UUID: b44f95c4-305e-432a-9d2f-c4aa89c5f644

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:49

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
TRANSPORTATION DEPT
Athey Creek Consultants, LLC
B26096
Integrated Corridor Management (ICM) Stage 3 – Dep
93947
The purpose of this contract was to assist MnDOT in the following: 1) develope a US DOT Application for the Integrated Corridor Management (ICM) Stage 3 Project, 2) develop request for proposals to solicit contractors for implementation of ICM Stage 3 when funded, and 3) assist MnDOT in ICM Stage 3 deployment when funded.
This contract was necessary to continue the work started in the ICM Stage 1 Project of which Minnesota was one of eight locations selected by the FHWA to develop a concept of operations.
Project Duration
Wed, 03/18/2009 - 00:00
Tue, 06/30/2009 - 00:00
Thu, 09/30/2010 - 00:00
Yes
{Empty}
Contract Amounts
$63608.03
$54066.20
$117674.23
Yes
State ITS Funds
No
{Empty}
Brian Kary
Brian.kary@state.mn.us
Contractor provided deliverables in a timely manner.
Quality of the work was very good. Contractor met the needs of the project.
Contractor costs were reasonable.
The Contractor is easy to work with and provided quality work in a timely manner. The Contractor’s services would be used again.
Yes
{Empty}
4 - satisfied