Submission Number: 13017
Submission ID: 63481
Submission UUID: 26c13798-a2a8-42ed-b6da-0acb45c09b4e

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:49

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
Military Affairs Dept
Liesch Associates, Inc.
441617
Design for Removal of Hazardous Materials, AHATS
8602
Design Services for hazardous materials abatement of 11 buildings in Arden Hills Army Training Site. Services provided include project coordination with the contractor and facility, preparation of specifications, processing of contractor pay requests, and project closeout report preparation.
Project Duration
Mon, 06/20/2011 - 00:00
Sat, 12/31/2011 - 00:00
Sat, 12/31/2011 - 00:00
Yes
{Empty}
Contract Amounts
$6462.00
{Empty}
$6460.11
Yes
100% Federal
Yes
Single Source Rotation based on RECS Hazardous Materials Master Contracts for Design.
Ken Auer
ken.auer@us.army.mil
The project design (PD) contractor timeliness was poor. Final report was three months overdue. It took intervention by our office, with repeated emails/calls, for the PD contractor and abatement contractor to put aside their differences, and produce the required information.
Contractor had to be repeatedly reminded of the need to provide timely project updates. When they did provide reports, the majority of the time the PD contractor simply forwarded the Air Monitoring contractor’s field notes.
PD contractor’s quality was poor. They did not provide consistent oversight responsibilities, but instead, relied on the air monitoring contractor to perform this function. PD contractor rarely visited the site. There is supposed to be a separation between the Air Monitoring contractor and the Project Design/Abatement contractors.
When repeatedly asked for the status of the final report, contractor seemed unaware of the timing or unconcerned with the delay.
Abatement contractor was allowed to leave the site without providing all the required recycling reports, manifests and bills of lading. Abatement contractor claims they were not given clear guidance on what information the PD contractor required to complete the final report.
Note: Air monitoring contractor provided their final report within two weeks of project completion.
Estimated costs were not exceeded.
Overall performance was poor. Lack of oversight, lack of guidance and lack of timeliness, resulted in unnecessary delays. Proper oversight would have prevented this from happening. Submission of documents should have been an ongoing process between the abatement contractor and PD. Ensuring all required documents were delivered, should have been established from the get go.
Unfortunately performance level has been a recurring problem with this contractor. Delays in response, lack of oversight and delays in providing final reports.
No
{Empty}
2 - dissatisfied