Corrections Dept
Wold Architects and Engineers
444709
Design for Upgrade Well #1 and Chemical Feed
78902MLP
Design and construction administration for upgrading well #1 and its chemical feed.
Project Duration
Sun, 04/03/2011 - 00:00
Sat, 09/01/2012 - 00:00
Tue, 06/12/2012 - 00:00
Yes
{Empty}
Contract Amounts
$9780.00
$0
$9780.00
Yes
FY 09, Agy G02, Fund 500, Org 3298, Appr 38B
Yes
Budget under $25,000 and expertise of Wold with well work.
Ryan Allen
ryan.allen@state.mn.us
Adequate. There were a few minor issues that dragged the project on but it was the fault of the contractor and not Wold.
Good.
Very good.
Satisfactory.
Yes
{Empty}
4 - satisfied