Submission Number: 13212
Submission ID: 63676
Submission UUID: 28a7bed3-41c7-40ce-bfe9-6edca5ba8559

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:49

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
TRANSPORTATION DEPT
SRF Consulting Group, Inc.
B02766
T.H. 41 over Minnesota River Final Environmental I
90916
The purpose of this Contract was to provide a Final Environmental Impact Statement for the proposed new T.H. 41 Minnesota River crossing between T.H. 169 and T.H. 212.

A contract was necessary because MnDOT staff with the necessary expertise were unavailable to provide this one-time service when needed. This was an intensive undertaking, both technically and with public participation. In addition, this is a controversial project due to possible wetland impacts and a rare calcareous fen in the area. In order to gain approval from the local watershed district, the use of a more neutral party than state employees was desirable.
Project Duration
Fri, 06/29/2007 - 00:00
Tue, 06/30/2009 - 00:00
Fri, 12/30/2011 - 00:00
No
1911
Contract Amounts
$240350.64
{Empty}
$240350.64
Yes
Trunk Highway
Yes
In September 2002, SRF Consulting Group, Inc. was awarded a contract (Mn/DOT Agreement No. 83346) to provide a two phased transportation corridor and river crossing study for T.H. 41 across the Minnesota River between T.H. 212 and T.H. 169. The project was initially split into two phases. Phase 1 was the scoping study, intended to identify a set of transportation corridor alternatives, develop conceptual plans, evaluate impacts and prepare a scoping document from the perspective of making a location decision. Phase II was to be a tiered EIS sufficient to define preferred transportation corridor improvements and garner local, regional, state and federal approvals necessary to preserve right-of-way for the preferred transportation corridor improvement.

The purpose of Phase 2 was to produce the draft and final environmental impact statements, and also included significant additional wetlands-related tasks, in particular at Seminary Fen. It was originally assumed that Seminary Fen was sufficiently far from the project area that it need not be considered. However, due to the sensitive and delicate nature of this fen, and the risk that this project could damage it, consideration of the fen is a crucial element in obtaining permits from affected watershed districts, the Army Corps of Engineers, etc. The Seminary Fen study added considerable work and time to the contract.

During the course of the scoping study, MnDOT requested that two additional build alternatives be studied and carried forward into the environmental impact statement. This work also added time to the contract.

In summary the project would soon be complete through the Draft EIS. The contract was then be near the five year statutory limit for professional/technical contracts. The Final EIS needed to be completed, and could not be finished before the five year limit is reached. When it became apparent the Final EIS could not be completed within the five year statutory limit, tasks for the Final EIS were removed from the original contract. The Draft EIS/Final EIS split was picked as the transition point for the original contract to a new contract. MnDOT Contract No.90916 was be a continuation of services from MnDOT Agreement No. 83346.

SRF Consulting Group, Inc. was clearly and legitimately the single source of the proposed services for the following reasons:
• Additional tasks outside the control of SRF, particularly the work on Seminary Fen, and the time to complete those tasks were added to the original contract. The result is the Final EIS could not be completed within the five year statutory limit. Therefore, an amendment to the existing contract was not feasible. Had it not been necessary to perform the additional work, all tasks would have been completed within five years.
• The Final EIS was an intense undertaking, both technically and with public participation. SRF was completely familiar with the project, having done all work done through the Draft EIS. If the remaining work were to be awarded to a new consultant, there would likely have been a considerable amount or re-work, resulting in significant additional time and costs to the State.
• This is a controversial project, particularly when dealing with local watershed districts. SRF had developed trust in dealing with these stakeholders. Switching to a different consultant at this point could have upset the various interest groups and aggravated the political situation.
Diane Langenbach
diane.langenbach@state.mn.us
SRF was very responsive and flexible when the collaboration process to build agreement on a corridor took much more time than expected
SRF delivered a quality product both on the technical process and the stakeholder engagement process.
SRF’s costs were appropriate for the size of the FEIS and the complexity of building stakeholder agreement on a future T.H. 41 Minnesota River crossing corridor
SRF, with support from Anne Carroll (public participation subconsultant) did excellent work on this project.
Yes
{Empty}
5 - very satisfied