Public Safety Dept
Aeritae Consulting Group
38538
11G Solaris Upgrade Project
{Empty}
The BCA required the professional technical services of a Architect Senior resource to assist in the 11G Solaris Upgrade Project. The resoure provided assessment, configure, and document of BCA's test and production Solaris server environments for the Oracle 11G project.
Project Duration
Thu, 12/01/2011 - 00:00
Tue, 01/31/2012 - 00:00
Sat, 06/30/2012 - 00:00
Yes
{Empty}
Contract Amounts
$32000.00
$0.00
$32000.00
Yes
State General Funds
No
{Empty}
Kurt. Augustine
Kurt.Augustine@state.mn.us
All work was completed within the timeframes set.
The technical work provided by Contractor's resource, David Paschall-Zimbel waas very detailed and exceeded expectations.
The Contractor's hourly rate was consistent with the rates of of similar resources.
Services provided by David Paschall-Zimbel were well organized and met BCA's expectations for the project.
Yes
None
4 - satisfied