Submission information
Submission Number: 13376
Submission ID: 63840
Submission UUID: 57bead8c-d2c6-41e2-99c5-2ba92a7132ec
Submission URI: /form/vendor-performance-evaluation
Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:50
Remote IP address: (unknown)
Submitted by: admin
Language: English
Is draft: No
Current page: webform_submission_import
Webform: Vendor Performance Evaluation
Locked: Yes
The on-time of the deliverables and project-related cooperation is rated as poor. The consultants did not deliver feasibility study project artifacts, nor did the consultants complete project deliverables on-time. Even though the consultants jointly developed a project schedule with MnDOT, the consultants did not deliver project work based on this schedule. In some cases, the consultants delivered the same artifact repeatedly even though it was rejected by the project team. In one instance, an approach presentation was given three times and each time the consultants were told to present a different approach only to come back again with the same slide deck.
QA/QC Plan Conformance is not applicable in this situation. The QA/QC plan was a deliverable on the project schedule that the vendor did not deliver to MnDOT and, therefore, could not be evaluated.
Oracle was really difficult to enter into contract with. It took quite some time to negotiate a contract initially. We ended up using their forms for the contract because they would not agree to use MnDOT’s standard forms.