Submission Number: 13420
Submission ID: 63884
Submission UUID: d330d479-d5eb-4bae-b6a9-2048c4479754

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:50

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
Administration Dept
Roof Spec Inc
40093
Heat Tape Installation
02SO0007
Existing roof tiles were discovered to be loose and needed to be documented before and after a heat tape installation project to assess repairs and responsibility.
Project Duration
Mon, 02/13/2012 - 00:00
Sun, 09/30/2012 - 00:00
Sun, 09/30/2012 - 00:00
Yes
{Empty}
Contract Amounts
$1000.00
$0.00
$1000.00
Yes
Agency
Yes
Amount is within guidelines for single source. This consultant did previous study and this was an update.
Glen Heino
glen.heino@state.mn.us
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Yes
n/a
4 - satisfied