Faribault Academies
Environmental Management Associates, Inc.
35919
MSAD Asbestos Abatement/Lead Stabilize Pollard Smi
44119DAP
Window replacement project at Pollard and Smith Halls required separate project for abatement of haz mat containing caulking and paint.
Project Duration
Mon, 10/17/2011 - 00:00
Tue, 07/24/2012 - 00:00
Mon, 10/22/2012 - 00:00
Yes
{Empty}
Contract Amounts
$9500.00
$1500.00
$11000.00
Yes
FY10 AP
Yes
On master roster of haz mat vendors rotated through sites and within allowable limits. saved money on construction part by making this a bid project.
Glen Heino
glen.heino@state.mn.us
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Yes
n/a
5 - very satisfied