TRANSPORTATION DEPT
University of Minnesota
3000021907,3090461
MnDOT Design Bid Build Quality Management Process
89261w259
Mn/DOT has been striving to improve quality within our project development process and deliverables for several years. There have been recent instances where less than adequate quality has resulted in plan errors or inconsistencies that have led to delays in project letting and/or award and in some cases rejection of all bids. This has resulted in additional cost not only to citizens of the state but to external partners involved in the delivery of these projects.
With this training the department will establish consistent statewide guidelines for quality management practices within project development. This will result in identification of high risk error occurrence to enhance opportunities for correction in advance of project development turn in deadlines and letting. The end result will be construction plans that are biddable and constructible with a reduced incidence of complex addenda, bid rejection, and high value change orders and supplemental agreements due to plan errors or inconsistencies.
Project Duration
Mon, 02/07/2011 - 00:00
Fri, 09/30/2011 - 00:00
Fri, 08/31/2012 - 00:00
Yes
{Empty}
Contract Amounts
$119985.00
$31869.00
$151854.00
Yes
Trunk Highway
No
{Empty}
Valerie K. R. Svensson
Valerie.svensson@state.mn.us
All work was completed in a timely and expedited manner. The consultant was very responsive even when timelines were very short. The project did suffer delay in delivery due to the Government shut down in July 2010 and required an additional round of training classes in 2011
All work completed by the team members was of very high quality. Team members have a high level of expertise and provided exceptional support.
Costs were within dollar values expected. Given the nature of the work, delivery was enhanced with consultant support.
Overall performance was exceptional. Team members integrated well with internal staff, District personnel and external participants
Yes
{Empty}
5 - very satisfied