Faribault Academies
I&S Group
439472
Relocate Lysen Administrative Offices
44084BAP
Project was used to help prevnet peolple entering the building and not being able to get directed or find their contact.
Project Duration
Thu, 05/22/2008 - 00:00
Wed, 10/01/2008 - 00:00
Sun, 05/01/2011 - 00:00
No
{Empty}
Contract Amounts
$45496.75
$20320
$65816.75
Yes
2006 G02 500 3241 36A
No
{Empty}
Ken Bronson
ken.bronson@state.mn.us
The consultant's timeliness on this project was good for phase 1, but extremely poor for Phase 2.
The quality of the work done was poor on phase 2. There were constant questions and discrepancies that created additional costs throughout Phase 2.
Good cost for averqage consultant fee, but not worth the lack of service received.
Poor, very ignorant for a professional firm.
No
{Empty}
1 - very dissatisfied