TRANSPORTATION DEPT
LHB, Inc.
3000028473
Boundary to Scanlon Thick Overlay Plan
96022
Detailed design plan for overlay on I-35 project documentation.
Project Duration
Mon, 02/08/2010 - 00:00
Sat, 07/31/2010 - 00:00
Thu, 05/31/2012 - 00:00
No
{Empty}
Contract Amounts
$241524.00
$375185.70
$616709.70
No
Trunk Highway
No
{Empty}
Todd Campbell
todd.campbell@state.mn.us
Good, given the project changes required of them.
Very good
Fair
Contractor did a fine job on this difficult, ever-changing project (funding sources and amounts changed more than once over this life of the contract). Communication was excellent throughout.
Yes
{Empty}
4 - satisfied