TRANSPORTATION DEPT
SEH, Inc
B55213/24747
TH 60 Gaps Supplemental Final EIS
98352
FHWA required MnDOT to prepare a Supplemental Final EIS for the TH 60 Gaps. There was not available expertise for the environmental studies and not available staff for the writing.
Project Duration
Mon, 04/18/2011 - 00:00
Fri, 11/30/2012 - 00:00
Fri, 11/30/2012 - 00:00
Yes
{Empty}
Contract Amounts
$285527.00
{Empty}
$285527.00
Yes
Bond
No
{Empty}
Peter Harff
Peter.harff@state.mn.us
SEH provided all of their deliverables on or ahead of schedule, often turning things around extra quickly to make up for late reviews by FHWA
The documents required very little editing and virtually none of those required were substantive. The quality was excellent.
The project came in about $50,000 under budget. They dealt with issues quickly and efficiently. They used limited staff so there was no need to keep many people engaged. It was well managed and the cost was right.
This was excellent work by the consultant. I switched jobs about half way through the project, but they kept everything moving along. This was the easiest contract to manage, yet the product was very well done.
Yes
None
5 - very satisfied