Public Safety Dept
Televate, LLC
B51065
Wireless Data Network Requirement
{Empty}
To supply the state of Minnesota with the necessary information to prepare for integration with the nationwide Public Safety Wireless Broadband Network. This includes a user needs assessment, network implementation model, funding models, and other components. This project was necessary to prepare Minnesota for the next generation of public safety interoperable communications.

Minnesota did not possess the resources to perform this specialized work internally and with impartiality, and so it procured outside services.
Project Duration
Mon, 11/15/2010 - 00:00
Mon, 12/31/2012 - 00:00
Mon, 12/31/2012 - 00:00
Yes
{Empty}
Contract Amounts
$200000.00
$50000.00
$250000.00
Yes
Statewide Radio Board
No
{Empty}
Jackie Mines
jackie.mines@state.mn.us
Acceptable, but not exceptional.

Most deliverables were delivered in a timely manner. The final deliverable from the original scope of work, and the single deliverable added during the amended scope of work, were both delivered technically within the performance period of the contract but on the last acceptable day. This meant there was a constrained period to review and accept the deliverables.
Exceptional.

The contractor was extremely qualified in all aspects to perform the work. The contractor provided responsive and effective customer support and all final deliverables were fully successful.
Exceptional.

The contractor bid the project at a competitive cost. Additionally, the contractor performed significant work above and beyond their original bid offer without requiring additional payment, effectively reducing their hourly rate significantly.
Exceptional.

The contractor fully performed all work required under the contract and exceeded our expectations for the work and the work included in the contractor’s original proposal.
Yes
{Empty}
5 - very satisfied