Administration Dept
Meyer, Scherer & Rockcastle, Ltd
49275
De-commission Data Centers Predesign
02CP0007
Needed single source design team selected by SDSB to Pre-design in preparation for various Capitol complex moves anticipated for data center moves after consolidation; and Capitol occupant moves to accommodate resotration activities.
Project Duration
Thu, 08/02/2012 - 00:00
Thu, 01/31/2013 - 00:00
Thu, 01/31/2013 - 00:00
Yes
{Empty}
Contract Amounts
$18561.00
$0.00
$18561.00
Yes
FY 11 Agency funds
No
SDSB process used
Glen Heino
glen.heino@state.mn.us
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Yes
n/a
5 - very satisfied