TRANSPORTATION DEPT
URS Corporation
3000029871
Critical Path Management for Un-Bonded Concrete Ov
98502
The purpose of this Contract was to provide construction schedule, critical path management: baseline review, monthly schedule review, constructability, time impact analysis, recovery and claim support for an unbonded concrete overlay project on I-35E from CSAH 96 to the north junction with I-35W.
Project Duration
Fri, 05/20/2011 - 00:00
Wed, 11/30/2011 - 00:00
Fri, 11/30/2012 - 00:00
Yes
330
Contract Amounts
$43589.50
{Empty}
$43589.50
Yes
Trunk Highway
No
{Empty}
Garrett Schreiner
garrett.schreiner@state.mn.us
Finished on schedule
Good quality
Done under budget
Very good
Yes
{Empty}
5 - very satisfied