Submission Number: 13871
Submission ID: 64335
Submission UUID: 5d2d6fdd-432a-4882-9023-6089e0cea94e

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:50

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
TRANSPORTATION DEPT
HDR Engineering Inc.
3000076541 (FY 13)
Preliminary and Final Design for replacement of Ca
97139
This Contract was for project development of the Cayuga and Maryland Avenue bridge projects through final design and concept development of traffic alternatives along the I-35E corridor from downtown St. Paul to the northern suburbs.

The Cayuga bridge is on the Chapter 152 list of bridges considered to be fracture critical, and needs to be replaced. The legislature approved funding to advance the project sooner than anticipated.
Project Duration
Fri, 12/17/2010 - 00:00
Sat, 06/30/2012 - 00:00
Tue, 04/30/2013 - 00:00
Yes
67536
Contract Amounts
$6057271.26
$2335426.39
$8392697.65
Yes
State Bond Funds
No
{Empty}
Josephine (Joey) Lundquist
Joey.Lundquist@state.mn.us
The consultant accomplished the tasks assigned in the timeframe we asked for. The project was delivered on time.
Dan Dorgan and Steve Jensen were excellent project managers for the project and produced and excellent product.
The cost was what was to be expected from a consultant.
Overall, I was happy working with HDR and the sub-consultants. They accomplished the task assigned and got us the answers and construction plans we asked for.

However, there are many negative aspects of having a contractor prepairing construction plans with so many subcontractors:
- The plans are split into many pieces and required more sheets than if one consultant had one it.
-The cross sections in the plans were more complicated due to how the project was split between the sub-consultants .
-There was much more coordination than if we were working with one company (they each had to be consistent with each other and have coordination meetings with the sub-consultants).
-It was more expensive due to the extra coordination with sub-contractors (would have been much cheaper and more efficient with one consultant doing the design).

I would not recommend having so many sub-consultants on a project in the future.
Yes
{Empty}
5 - very satisfied