TRANSPORTATION DEPT
WSB & Associates, Inc.
3000084856 3000043007
Design Review Services
631
Support the delivery of special program and regular program projects including plan review, earthwork and quantities analysis and verification, development of unique special provision, and development of contract provisions and proposals for project letting. Current staffing levels cannot support the work required given elevated program levels and workload balancing limitations.
Project Duration
Fri, 02/10/2012 - 00:00
Tue, 07/31/2012 - 00:00
Thu, 01/31/2013 - 00:00
Yes
{Empty}
Contract Amounts
$99550.00
{Empty}
$99550.00
Yes
Trunk Highway
No
{Empty}
Valerie K. R. Svensson
Valerie.svensson@state.mn.us
All work was completed in a timely and expedited manner. The consultant was very responsive even when timelines were very short. Contract funds were expended several months before the anticipated contract end date to extreme work load levels.
All work completed by the team members was of very high quality. Team members have a high level of expertise and provided exceptional support.
Costs were within dollar values expected. Given the volume of work that was produced during this time, delivery was enhanced with consultant support.
Overall performance was exceptional. Team members integrated well with internal staff and District personnel.
Yes
{Empty}
5 - very satisfied