TRANSPORTATION DEPT
Short Elliott Hendrickson Inc.
3000081900
Phase II Investigation and Geotechnical Oversight
1915
MnDOT plans to reconstruct TH 36 from approximately Tuenge Drive to CSAH 23 (Beach Road) as part of the Stillwater Bridge Project. The project includes construction of a new interchange at TH 36 and Osgood Avenue, roadway reconstruction and frontage road construction, a bridge over TH 36 for CSAH 23, potential storm water ponds, utilities, etc. A frontage road extends past CSAH 23 on the south side of TH 36 that will tie into Stagecoach Trail. The purpose of this contract was to environmental oversight for geotechnical borings, document the work and properly dispose of cuttings. The Minnesota Pollution Control Agency (MPCA) is requiring a report documenting all of the field work specifically associated with the landfill. In order to provide the MPCA with the documentation that they are requiring and in the format the MPCA requires, an environmental contractor familiar with the project has to oversee the geotechnical borings. This information will be used by MnDOT to determine final project design plans and specifications and meet MPCA requirements.
Project Duration
Fri, 09/07/2012 - 00:00
Mon, 09/01/2014 - 00:00
Sat, 05/25/2013 - 00:00
Yes
{Empty}
Contract Amounts
$76825.48
{Empty}
$76825.48
Yes
Bond
No
{Empty}
Keri Aufdencamp
keri.aufdencamp@state.mn.us
Good
Good
Acceptable
Good
Yes
{Empty}
4 - satisfied