Corrections Dept
Erickson Ellison @ Associatesw (EEA)
56933
Low Pressure Steam Study
78SC0029
A study was needed to verify if there were any savings for the State by switch the St Cloud prison from high pressure steam to low pressure.
Project Duration
Thu, 01/24/2013 - 00:00
Fri, 05/10/2013 - 00:00
Wed, 07/10/2013 - 00:00
Yes
{Empty}
Contract Amounts
$14900.00
$2500.00
$17400.00
Yes
Facility
No
N/A
Roger Rooney
roger.rooney@state.mn.us
Report was timely. The only delay was owner requested supplemental work.
The report was good
The contract was a good value for the State
Good
Yes
No
4 - satisfied