Administration Dept
Ericksen Ellison and Associates, Inc.
39427
Design for Stassen Building Emergency Distribution
02RB0004
Cost to replace gear that failed required public bid and design documents prepared by an electrical Engineer.
Project Duration
Thu, 01/05/2012 - 00:00
Sun, 06/30/2013 - 00:00
Sun, 06/30/2013 - 00:00
Yes
{Empty}
Contract Amounts
$11000.00
$0.00
$11000.00
Yes
FY12 Agency
Yes
within guidelines, familiar with building issues
Glen Heino
glen.heino@state.mn.us
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Yes
n/a
5 - very satisfied