TRANSPORTATION DEPT
HDR Engineering, Inc.
55194
M-1 Alignment Seismic Study
2360
The purpose of this contract is to determine if a bridge can be constructed in an active mine. The effects of major regular blasts on a bridge structure need to be evaluated.
Project Duration
Fri, 11/09/2012 - 00:00
Mon, 09/30/2013 - 00:00
Tue, 04/17/2012 - 00:00
Yes
{Empty}
Contract Amounts
$99066.80
{Empty}
$105670.49
No
Trunk Highway
No
{Empty}
Keith Molnau
keith.molnau@state.mn.us
Report was delivered in with within expected timeframe given modified alignment info provided by MnDOT
High quality report some clarifications were needed and provided in comments back to Contractor
Cost was slightly over contract amount
The Contractor was fully engaged in project and developed report to summarize findings of vibration study and effect of vibrations on concept bridge types that were evaluated. Very good performance and cooperation throughout project.
Yes
{Empty}
4 - satisfied