TRANSPORTATION DEPT
Alliant Engineering, Inc.
3000112007
TH 252/47 Signal Optimization
3068
This Contract was for Contractor to provide signal optimization of 24 intersections along TH 252 and TH 4 7 in the Cities
of Brooklyn Park, Columbia Heights, Fridley, and Blaine. This will improve the coordination timing of the TH 252 and
TH 47 signals and result in reduced stops, delays, and fuel used.
Project Duration
Wed, 03/06/2013 - 00:00
Sun, 06/30/2013 - 00:00
Sun, 06/30/2013 - 00:00
Yes
{Empty}
Contract Amounts
$61952.47
{Empty}
$61952.47
Yes
State funds
No
{Empty}
Kevin Schwartz
Kevin.Schwartz@state.mn.us
This project had an unusually tight time line and the consultant delivered a quality product before the deadline.
The consultant delivered high-quality coordination timing plans on both corridors that had excellent two-way progression with the lowest possible delay for the cross street.
The cost per signal was good, especially given the tight-timeline.
This consultant has a lot of skill and experience in developing signal
optimization timing plans and that was shown in the results of this project which will save the public an additional $3.6
million/year in user benefits even though the corridors had coordination timing prior to project.
Yes
{Empty}
5 - very satisfied