TRANSPORTATION DEPT
SRF Consulting Group, Inc.
3000104320
Impact of Freight in Statewide Planning and Progra
2600
The Plan provides a policy framework to introduce freight considerations into statewide planning and programming decision process with regard to public infrastructure.
Project Duration
Fri, 01/18/2013 - 00:00
Wed, 07/31/2013 - 00:00
Sun, 06/30/2013 - 00:00
Yes
{Empty}
Contract Amounts
$99932.23
{Empty}
$99906.55
Yes
Trunk Highway
No
{Empty}
Jarrett Hubbard
Jarrett.Hubbard@state.mn.us
Above Average, Contractor never was the cause of delays.
Average, Contractor met MnDOT’s expectations
Average, Similar product would cost the same elsewhere.
Average, Completed all requested tasks.
Yes
{Empty}
4 - satisfied