TRANSPORTATION DEPT
HNTB Corporation
3000079250 / 3000005938
Structural Stabilization of the Stillwater Lift Br
98862
This Contract was executed to provide detail design services for structural, mechanical, and electrical repairs to the Stillwater Lift Bridge. The historic nature of the bridge required specialized expertise to address the various issues with the structure. The Bridge Office does not have expertise handling the design of repair details for a historic lift bridge, and MnDOT as an agency does not possess the mechanical and electrical expertise that was required for this project.
Project Duration
Thu, 08/18/2011 - 00:00
Fri, 08/31/2012 - 00:00
Thu, 02/21/2013 - 00:00
Yes
{Empty}
Contract Amounts
$200791.99
$65814.77
$266606.76
Yes
Trunk Highway
No
{Empty}
Paul Kivisto
paul.kivisto@state.mn.us
Submittals were all on time.
Quality was very good
Project finished within budget.
The Contractor did a very good job evaluating all of the corroded members, providing repair details, and providing adequate special provisions. Performed majority of work without much input from MnDOT
Yes
{Empty}
5 - very satisfied