TRANSPORTATION DEPT
Parsons Brinckerhoff, Inc.
3000121920, 3000149859
Baudette Bridge Project – Design and Construction
3305
This contract was part of the project to replace the bridge at the international crossing between Baudette, MN, and Rainy River, Ontario. The purpose of the contract was to have the Consultant identify and document the differences between the design and construction standards of transportation projects in Minnesota and Ontario. This was done so that any areas of potential conflict could be identified early in the project to avoid schedule delays.
It was necessary to enter into a contract because the District and the Bridge Office did not have adequate staff to complete the task in the desired timeframe, nor the knowledge of the standards used in Ontario, Canada.
Project Duration
Mon, 05/06/2013 - 00:00
Wed, 07/31/2013 - 00:00
Sun, 09/01/2013 - 00:00
Yes
{Empty}
Contract Amounts
$92283.18
{Empty}
$92283.18
Yes
Trunk Highway
No
{Empty}
Tony Lesch
Tony.lesch@state.mn.us
All of the requested tasks were completed on-time or ahead of schedule.
All items received were of sufficient quality, including the final deliverables and intermittent draft deliverables.
Project was completed for the amount of the estimated budget.
Overall the Contractor’s performance was satisfactory to meet the project goals. There were some delays in obtaining the requested data, but this appeared to be mainly due to difficulties in coordinating with staff from the Ontario Ministry of Transportation. The project’s goals and timelines were ultimately met.
Yes
{Empty}
4 - satisfied