Administration Dept
Klein McCarthy & Co.
53122
Replace Ceiling Tiles in Complexes 1-3-4
78RC0004
Design and construction administration for replacing existing ceiling tile that was falling down in complex wings 1-3-4 at MCF Rush City.
Project Duration
Mon, 09/24/2012 - 00:00
Thu, 09/18/2014 - 00:00
Fri, 09/20/2013 - 00:00
Yes
{Empty}
Contract Amounts
$15750.08
$0.00
$15750.08
Yes
Agency
Yes
Agency had worked with Klein McCarthy successfully, Klein McCarthy was available to do the work, and the estimated fee was less then $ 25,000 threshold.
Gary A Krocak
gary.krocak@statre.mn.us
Klein McCarthy was timely. They completed work as requested and as needed, finishing work on schedule.
Contract documents met contract requirements. Only one change to the contract, which was requested by the facility.
Reasonable.
Performance was acceptable, meeting the contract requirements and needs of the facility.
Yes
{Empty}
4 - satisfied