TRANSPORTATION DEPT
Bolton & Menk, Inc.
3000115147 & 3000147677
Contract Administration and Inspection on S.P. 481
1908
The consultant was hired to provide contract administration and inspection on S.P. 4812-83 (TH 169) because it was determined that MnDOT did not have adequate qualified personnel available to provide these services the year the project was built due to staff reductions and an increased workload that construction season.
Project Duration
Tue, 04/02/2013 - 00:00
Tue, 12/31/2013 - 00:00
Tue, 12/31/2013 - 00:00
Yes
{Empty}
Contract Amounts
$368642.51
{Empty}
$368642.51
Yes
Trunk Highway Funds – Better Roads
No
{Empty}
Tony Hughes
tony.hughes@state.mn.us
Contractor’s project manager was great to work with and was very responsive. All required field work was done in a timely manner; however, it took longer than anticipated to get the final project documentation submitted.
On a scale of 1to 10; Contractor Quality was a 8.0
MnDOT received good value for the money spent.
Contractor’s project staff did an excellent job making sure project was constructed in close conformity with Special Provisions, Plans, and Specifications. The Contractor’s project manager, Darrick Anderson, was great to work with. He responded immediately to any requests and did a good job keeping up to speed on required project documentation (i.e. work orders, change orders, SA’s, etc.). It did take longer than anticipated to get the final project documentation from the Contractor and several errors were discovered when the information was reviewed by the Office Manager, however, in general the Contractor performed well.
Yes
{Empty}
4 - satisfied