Administration Dept
Ericksen Ellison and Associates
50650
Replace Main Boiler Burners
78SW0013
Services to design and administrate replacement of old and inefficient main boiler burners at MCF Stillwater.
Project Duration
Mon, 08/20/2012 - 00:00
Sat, 08/02/2014 - 00:00
Thu, 09/19/2013 - 00:00
Yes
{Empty}
Contract Amounts
$12100.00
$0.00
$12100.00
Yes
Agency
Yes
Estimated fee was below the $ 25,000 threshold. EEA was familiar with the boiler burners at the facility as they were involved in the replacement of two other boiler burners in the same building.
Gary A. Krocak
gary.krocak@state.mn.us
Satisfactory. Met facility schedule needs.
Acceptable. No significant construction changes.
Reasonable - cost effective.
Acceptable. No significant issues.
Yes
{Empty}
4 - satisfied