Corrections Dept
Inspec Inc
54748
MCF FRB Roof Replacement Master Controls, Power Pl
78FA0023
Replace various lagging roofs.
Project Duration
Thu, 11/01/2012 - 00:00
Sat, 10/25/2014 - 00:00
Sun, 04/06/2014 - 00:00
Yes
{Empty}
Contract Amounts
$19900
$4500
$24400
Yes
2012 3600 G0233329 G0215A8 78FA0023
No
{Empty}
Ken Bronson
ken.bronson@state.mn.us
Design went well through the bidding phase. After the work was awarded, there was a poor job in getting the contractor started and getting the work substantially finished.
Good quality of work and detailing.
Very reasonable for the size of project.
Unacceptable.
Yes
{Empty}
1 - very dissatisfied