TRANSPORTATION DEPT
Parsons Brinckerhoff, Inc.
3000150931
I-94 Between Highway 101 and Highway 241 – Cost Es
98875WO38
The contract provided enough design work to determine a reliable cost estimate for a design build contract. The district did not have staff available to provide the work due to the accelerated schedule imposed.
Project Duration
Thu, 11/07/2013 - 00:00
Fri, 01/31/2014 - 00:00
Fri, 01/31/2014 - 00:00
Yes
{Empty}
Contract Amounts
$109999.55
{Empty}
$109999.55
Yes
Trunk Highway
Yes
Parsons Brinckerhoff, Inc. was already under contract with MnDOT.
Claudia Dumont
Claudia.dumont@state.mn.us
Excellent
Very Good
Very Good
Very Good
Yes
{Empty}
5 - very satisfied