TRANSPORTATION DEPT
Stonebrooke Engineering, Inc.
3000146567
Final Design Plan Set for Bridge Guardrail and App
4405
Design survey, in place topography and elevations, provide a Final Design Plan set for 8 bridge locations, no district personnel available into meet plan delivery schedule.
Project Duration
Thu, 09/12/2013 - 00:00
Thu, 07/31/2014 - 00:00
Tue, 12/10/2013 - 00:00
No
1068.75
Contract Amounts
$94917.36
{Empty}
$107997.97
No
Trunk Highway
No
{Empty}
Chuck Slama
chuck.slama@state.mn.us
Contractor requested moving the 90% delivery back a week; did not deliver 3.5.3.4 until December 18th.
Contractor did not deliver the following items: 3.5.2.5 or 3.5.4
The final plans are between 25% to 30% standard plan sheets. The cost to produce a plan with this many standard sheets seems on the high side.
There was a considerable amount of MnDOT time spent trying to keep this Contract going. However, in the end MnDOT received a plan that still needed work to address quality concerns.
No
MnDOT had to take over the 95% plan and perform all QMP documentation work and incorporate all CO comments.