TRANSPORTATION DEPT
Parsons Transportation Group, Inc.
49675
TH 210 Emergency Reconstruction Support
1710
Extensive flooding in northeast Minnesota in June 2012 necessitated the initiation of an emergency design contract to rebuild washed out bridges and sections of roadways along Trunk Highway 210 and in the Forbay Lake area. The volume of bridges and roadways affected was so great that consultant assistance was critical to complete the project.
Project Duration
Thu, 07/19/2012 - 00:00
Sat, 08/31/2013 - 00:00
Tue, 12/31/2013 - 00:00
Yes
{Empty}
Contract Amounts
$401240.72
$224838.14
$626078.86
Yes
Federal
No
{Empty}
Keith Molnau / Angel Staples
keith.molnau@state.mn.us
The Contractor succeeded in meeting project deadlines.
The Contractor met quality standards.
This was a rush project so the cost was unusually high. It seemed to meet the needs of the District.
The Contractor worked well within the scope of the contract.
Yes
none
4 - satisfied