Submission Number: 27161
Submission ID: 110261
Submission UUID: e834b5a3-6453-4d71-8b41-0447e87ecfce

Created: Thu, 09/19/2024 - 13:27
Completed: Thu, 09/19/2024 - 13:27
Changed: Fri, 09/20/2024 - 14:18

Remote IP address: (unknown)
Submitted by: dalia.jorge
Language: English

Is draft: No

Locked: Yes
Transportation Department
Toltz, King, Duvall, Anderson and Associates, Inc
156220
Final Design - Bridge 69X19 (Miller Creek), Twin Ports Interchange
1032854
The purpose of the contract was to design and produce construction plans/specs for a complex culvert on the TPI project that
contained many complexities, including: complex staging, multiple foundation types, rail and HL-90 loading, etc.
Project Duration
Thu, 04/18/2019 - 00:00
Thu, 02/29/2024 - 00:00
Sat, 10/31/2020 - 00:00
Yes
{Empty}
Contract Amounts
$189790.59
$16590.39
$206380.98
Yes
state funds and bond funds
No
{Empty}
Johnson,Karl Andrew
Karl.Johnson@state.mn.us
Very Timely.
Great quality.
Appropriate
good
Yes
{Empty}
4 - satisfied