TRANSPORTATION DEPT
Michael Baker Jr., Inc.
46953
Final Design of Bridge 62925
910
The purpose of this contract was to complete final bridge design services for Bridge 62925, which is part of the Cayuga interchange reconstruction in St. Paul, Minnesota. The Bridge Office designed some of the project’s bridges in-house, but other bridges that required consultant assistance due to structural complexities and an aggressive timeframe for project completion.
Project Duration
Fri, 05/04/2012 - 00:00
Thu, 02/28/2013 - 00:00
Fri, 05/31/2013 - 00:00
Yes
{Empty}
Contract Amounts
$580229.36
$16390.33
$596619.69
Yes
BOND
No
{Empty}
Karl Gronvall / Nick Haltvick
karl.gronvall@state.mn.us
Satisfied
Satisfied
Satisfied
Satisfied
Yes
NONE
4 - satisfied