Submission Number: 15251
Submission ID: 65715
Submission UUID: 0e25e200-d80d-4777-a7b4-68fcc65f47cc

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:52

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
Pollution Control Agency
Regents of the University of Minnesota
B02648
Storm Water Infiltration- Soils amended w/Compost
{Empty}
This research is necessary to protect the health and environment of Minnesota citizens.
Project Duration
Thu, 06/28/2007 - 00:00
Tue, 12/01/2009 - 00:00
Tue, 12/01/2009 - 00:00
Yes
{Empty}
Contract Amounts
$40000.00
{Empty}
$40000.00
Yes
R32/330/D537/GF
No
{Empty}
Christopher Klucas
christopher.klucas@state.mn.us
The contractor's maintenance of the grant schedule was unsatisfactory. The project was completed within the original schedule, but deliverables were not received on time and staff turnover led to complications with the timeliness of the project.
The contractor provided clear and complete reports with good-quality data. The work plan objectives were met.
The budget was managed well. The contractor submitted invoices correctly; there were no disputed invoices. One change order and one amendment were needed: the change in grant managers necessitated some charges to the budget. However, overall the goals and objective of the project remained the same and were met in the project.
This project had one major difficulty: the day of the award, the principal grantee (the Department of Agriculture) had a staffing change and the contract manager was no longer able to manage the grant. The U of M became the grantee and manager of the project. This has pretty much been a nightmare as the U of M changed its accounting system during the time frame of the grant, and there have been many, many difficulties in trying to figure out who was doing what and dispursing the funds. This resulted in the project starting a year late, and the extended time needed to pull together the final report. All work was completed within the time frame of the grant, but because this project depended on the growing season and not the fiscal year, the final results were not known until September 2009.
Yes
{Empty}
4 - satisfied