Pollution Control Agency
Minnesota Environmental Initiative
B20402
Integrated Solid Waste Management Stakeholder Proc
{Empty}
The State is in need of a Contractor to design, lead and facilitate a stakeholder process to develop the elements of a plan to implement the recommendations from the Minnesota Climate Change Advisory Group.
Project Duration
Sun, 09/28/2008 - 00:00
Tue, 06/30/2009 - 00:00
Thu, 12/31/2009 - 00:00
No
{Empty}
Contract Amounts
$138985.09
{Empty}
$138985.09
Yes
330 B315 G19 NOMA
No
{Empty}
Tina Patton
tina.patton@state.mn.us
The project was not finished on time because the stakeholders requested more time. However, the contractor could have improved their schedule maintenance so that less time was necessary.
The contractor provided deliverables of good quality
The contractor had good budget management. One contract amendment was needed because the extension of time increased costs.
The contractor was very organized, had good attention to detail, was good at planning. However, in certain instances, MEI made its own internal decisions that it would not change to accomodate the needs of the MPCA. They explianed they did not consider MPCA a customer, but rather a partner. On two occasions they moved forward with actions before consulting the MPCA. There were aspects of working with this contractor that were very good, and in the end we were left with a mostly positive product, but due to some of the struggles we had, I would have to think about it and make sure that the project was a good fit before I hired this contractor again.
Yes
{Empty}
3 - neutral