Administration Dept
Braun Intertec Corporation
73594
Lot B Cap Complex Response Action Plan CCP Develop
02CP0036
Preparation of a site Response Action Plan/Construction Contingency Plan (RAP/CCP) under MN Pollution Control Agency's Remediation Control Program and subsequent geotechnical consulting services
Project Duration
Wed, 01/29/2014 - 00:00
Wed, 12/31/2014 - 00:00
Wed, 12/31/2014 - 00:00
Yes
{Empty}
Contract Amounts
$9550
$20000
$28550
Yes
Fund 3611, G0233381, G0215E5
No
Work was done under a master contract that had been competitively bid.
Gordon Christofferson
gordon.christofferson@state.mn.us
Contractor completed work on schedule.
Good
Good
They performed all requirements of their contract and within schedule.
Yes
{Empty}
4 - satisfied