TRANSPORTATION DEPT
HDR Engineering, Inc
210091
Statewide Electric Vehicle Infrastructure Deployme
1049804
Statewide Electric Vehicle Infrastructure Deployment Plan

The contract was necessary to complete the federally required Minnesota Electric Vehicle Infrastructure Plan in a short
timeline.
Project Duration
Fri, 04/01/2022 - 00:00
Fri, 09/30/2022 - 00:00
Sat, 07/30/2022 - 00:00
Yes
{Empty}
Contract Amounts
$99994.92
$4.35
$99999.27
Yes
TH
No
{Empty}
Simons,Siri Anne
Siri.Simons@state.mn.us
Very timely
High quality
Good value
good
Yes
{Empty}
4 - satisfied