TRANSPORTATION DEPT
KLJ Engineering LLC
164940
Windom Corridor Study, TH 60
1032725
MnDOT will be reconstructing the 4-lane state highway through this community in the future, and the corridor study helped
shape the future vision for the reconstruction project.
Project Duration
Thu, 08/22/2019 - 00:00
Tue, 03/30/2021 - 00:00
Thu, 06/30/2022 - 00:00
Yes
{Empty}
Contract Amounts
$467713.20
$106298.77
$574011.97
Yes
TH
No
{Empty}
Allis,Ronda Catherine
ronda.allis@state.mn.us
COVID required two contract extensions, but in the end the project was finished on time.
There were times through the process where better QA/QC should have been a higher priority.
Willing to take on additional tasks through contract amendment.
good
Yes
{Empty}
4 - satisfied